The stuff they don't teach at architecture school: Inside The Building Agency's enclosure blueprint

Written by

07 July 2026

 • 

7 min read

banner
The Building Agency's new fully integrated ENCLOSURE system is undergoing extensive BRANZ testing, revealing how structure, fire performance, moisture management and durability work together in real-world building assemblies.
The Building Agency's Design & Technical Manager, Jordyn Candy.
The Building Agency's Design & Technical Manager, Jordyn Candy.

When you're designing a building, it's easy to think about structure, fire performance, durability and weather-tightness as separate considerations. After all, they're governed by different sections of the Building Code, assessed through different tests and often discussed by different specialists. But in reality, they all arrive at the same place: the enclosure. 

It's where wind pressure, seismic movement, moisture management, fire performance and durability stop being individual compliance pathways and start interacting with one another, often in ways that aren't obvious until a project is already underway. 

For The Building Agency's Design & Technical Manager, Jordyn Candy, that's exactly where the interesting work begins. 

"Although we are testing our enclosure system one compliance pathway at a time," she says. "We're really testing how all these different requirements behave when they work together." 

The programme of testing through BRANZ, is about understanding how an entire wall assembly performs under pressure, and it covers everything from B1 Structure,  B2 Durability, through to C3 Fire Affecting Areas Beyond the Fire Source, and E2 External Moisture. 

The wind test that broke the machine 


Wind loading is one of those requirements that seems straightforward on paper until you start testing it. 

To establish compliance with B1 Structure, The Building Agency undertook P21 bracing testing through BRANZ, validating the performance of its sheathing board, fixing patterns and newly developed *ENCLOSURE Seismic Brackets. Full-scale wall samples were mounted into a test rig and repeatedly pushed from side to side until failure, generating the structural data required to calculate bracing performance. 

From there, the team moved into AS/NZS 4040.2 wind resistance pressure testing. 

Inside a large compression chamber, wall assemblies are subjected to increasing levels of suction until something gives, whether that's a fixing, a panel or the assembly itself. 

"It's basically a giant compression chamber that keeps increasing the pressure until something fails," says Candy. 

The first round of testing, using 600mm stud centres, achieved performance suitable for extra-high wind zones. But when the team returned with a 400mm stud configuration, the results surprised everyone. 

"We got to 7kPa and the board still hadn't failed. We didn't reach the limit of the system—we reached the limit of the test booth," shares Candy. "If architects want to save on timber costs, then the 400mm stud configuration is not required, but if it's 25m in the air and they have strong wind pressures, then we've proven our fixing to be pretty sturdy." 

An alternative fixing for a steel frame was also tested, and it also reached a standard suitable for extra-high wind zones. 

The result is a reminder that wind performance is never about a board in isolation. It's about the relationship between framing, fixings and the loads a building will experience over its lifetime. 

The Building Agency's ENCLOSURE Facade and Roofing Membrane.

Why fixing patterns matter 


One of the less obvious lessons from testing is that compliance requirements rarely operate independently. 

A wall assembly might achieve a particular wind loading result using one fixing pattern, then be fire-tested using another. While both tests may technically pass, the result can leave architects and specifiers navigating conflicting requirements. 

For The Building Agency, consistency became a key part of system development. 

The fixing patterns used to establish structural performance under B1 are replicated through the company's fire testing programme, creating a single pathway for specification rather than separate solutions for separate compliance requirements. 

It sounds like a small detail, but it's an important one. The more alignment that exists between testing conditions, the greater the confidence specifiers can have that the systems will integrate together and be compliant when the wall is built. 


What 1,000 degrees reveals about a wall 


In order to establish compliance with C3, The Building Agency undertook AS 1530.4 fire-resistance testing through BRANZ, installing a full wall assembly in front of a furnace operating at approximately 1,000°C. 

The objective isn't to see whether the outer layers survive but to measure how long the assembly can maintain its structural integrity, load, insulation performance and resistance to fire penetration. 

"In eight minutes the adhesive membrane made a very pretty green flame and just disintegrated, which is what we expected," says Candy. "But what we're really testing is the sheathing boards." 

The company's initial assembly achieved a one-hour fire rating, maintaining performance for 77 minutes before reaching insulation failure criteria. 

But it was the second test that revealed the next level of what was possible. 

Using a double-layer assembly with external *ENCLOSURE Stonewool insulation (a rock-based insulation pad), the wall absorbed extraordinary amounts of heat before fire began affecting the layers behind it. The insulation layer alone delayed heat transfer for more than two hours. 

The assembly ultimately remained in the furnace for four hours, which is the maximum duration permitted by the facility. 

"At the end they had to stop the test because the concrete in the furnace was glowing," Candy recalls. "They'd been throwing a thousand degrees at it for four hours." 

For architects accustomed to seeing fire ratings expressed as simple numbers on a specification sheet, the test offers a more tangible understanding of what those ratings actually represent. 

After four hours, the wall assembly still maintained integrity, but the concrete in the furnace was glowing.

The science of moisture 


If fire testing is dramatic, moisture management is almost invisible. 

Yet Building Code clauses B2 Durability and E2 External Moisture are arguably where some of the most important performance questions sit. 

Current BRANZ testing includes 90-day and 180-day weather exposure programmes, with samples left exposed to the elements before being retested for structural performance and durability. The objective is to determine whether the system performs after months of exposure in the same way it performs on day one. 

Alongside this, ASTM E96 water vapour transmission testing has been used to evaluate the interaction between the sheathing board and The Building Agency's vapour-permeable membrane. 

According to Candy, understanding moisture movement means looking beyond rain penetration alone. 

"Moisture doesn't only arrive through rain leakage," she explains. "It moves through air transport, vapour diffusion, capillary action and bulk water penetration. The question is how the wall manages that moisture once it's there." 

That thinking underpins the company's decision to pursue a fully adhered vapour-permeable membrane rather than relying on taped board junctions. 

The distinction may seem minor, but it reflects a broader philosophy around risk management. If the long-term performance of a wall assembly depends on perfect installation at every junction, those junctions inevitably become points of vulnerability. 

The goal is not simply to keep water out, but to create an assembly capable of managing moisture throughout its lifespan. 

The integrated ENCLOSURE system.
The ENCLOSURE Sheathing system.
ENCLOSURE-Vapour-Permeability-upscaled-by-Replicate.jpg

Beyond the standard façade system 


The next stage of development takes the ENCLOSURE system into territory more commonly associated with larger commercial buildings. 

Later this year, The Building Agency will undertake full-scale BRANZ testing EM7 and 4284 of its ENCLOSURE Flexihead channel. It's a detail designed to accommodate inter-storey movement caused by wind, seismic activity and structural deflection. 

The three-storey test will evaluate how the junction performs as part of a complete wall assembly, helping establish a compliance pathway for taller buildings and commercial-scale projects. 

The challenge is allowing the structure to move without compromising fire performance, weather-tightness or durability. It's the next step in a testing programme focused on 

understanding how the enclosure performs not just as a collection of individual components, but as a complete, integrated enclosure system. 

Disclaimer: *ENCLOSURE Seismic Brackets and *ENCLOSURE Stonewool are registered trademarks of The Building Agency