Relying on their expertise and proven ability to deliver innovative solutions, project sub-contractors, Mason & Hall Interiors, approached Forman with a request for 12.08-metre long studs to build a wall designed by an engineering firm for the unique cinemas.
With this project design, the steel studs could not be spliced and joined through the middle as that would create a weak point, so they needed to be rolled as one continuous piece. However, the longest off-the-shelf steel stud length available is only 7.2 metres.
So, Forman approached Studco to roll custom lengths of steel specifically for the Ormiston project. Knowing 12 metre studs would be a tricky task, the Studco manufacturing team needed to take extra precautions whilst producing the unprecedented studs. As the hollow C-section-shaped steel studs rolled off the machines, three people had to stand by ready to catch each one.
The next big task was to transport the studs from Studco’s manufacturing plant in Melbourne, Australia to the Forman distribution facility in New Zealand. This proved to be a challenge, as containers have a maximum capacity of just under 12 metres, but these studs were just over. They poked out slightly from the ends, but with a lot of care it was still achievable, and the studs arrived safely in NZ.
Despite the challenges involved, Forman and Studco worked closely to ensure a smooth process for the customer and deliver a product that could be installed quickly and easily, without any issues on the building site.